Current Projects

Completed Projects

Synthetic Turf Replacement

Locations:  Hall Stadium and Mercer Stadium

Project Team

Fort Bend ISD: 

Dean Lanuke, AIA
Project Manager

 Engineer:

Brooks and Sparks, Inc.
21020 Park Row
Katy, Texas  77449
David Barger, PE

 Contractor: Paragon Sports Constructors, Inc.
5001 Saunders Road
Fort Worth, TX 76119

 

Construction Duration – May-Aug. 2012

Construction Delivery Method – Competitive Sealed Proposal (CSP)

Construction Cost:  $1,316,370

Brief Description of Work

This project included replacement of the aging synthetic turf at Hall Stadium and Mercer Stadium as the existing turf seams had deteriorated, the field of play had developed waving in the surface due to subsurface changes, and the turf had exceeded its life expectancy.  

The new synthetic turf provides a safer cushion for athletes and enhance the sports facilities of FBISD. 